- Letter box installed
- Removalist arrives, the big move from Horsley to Kanahooka is underway
- Clothes line installed
- Landscapers complete the front garden
Monday, 25 November 2013
Sunday, 13 October 2013
October 2013
2/10/2013 - painters return and address some touch-up issues
3/10/2013 - cleaners arrive and address cleaning issues
4/10/2013 - handover with our site supervisor, the house is now ours
4/10/2013 - security system installed
8/10/2013 - stormwater drainage complete, our WCC bins are delivered
9/10/2013 - timber floor installation commences
9/10/2013 - concreting team commence formwork to paths and driveway
11/10/2013 - timber floor to living rooms is complete, carpet installed to bedrooms
11/10/2013 - landscaper arrives and commences work on retaining wall in back yard
11/10/2013 - contracts exchanged on the old family home, the house is sold
14/10/2013 - concreting to paths and driveway is complete
15/10/2013 - blinds and security doors installed
22/10/2013 - landscapers turf the back yard
23/10/2013 - landscapers install deck to front verandah and complete garden feature
24/10/2013 - landscapers turf the front yard and form front garden
25/10/2013 - carpenters return to install skirting boards
25/10/2013 - boundary fencing is complete
26/10/2013 - harvey norman arrives with our new fridge, dishwasher and smart tv
Friday, 6 September 2013
September 2013
05/09/2013 - vanity basins installed
05/09/2013 - gas connected to house
06/09/2013 - painters complete external painting
11/09/2013 - painting complete
12/09/2013 - tiling to ensuite bathroom complete
13/09/2013 - lights installed, electrical fitout is complete
13/09/2013 - internal plumbing complete
17/09/2013 - internal cleaners arrive
18/09/2013 - security fence removed
18/09/2013 - wardrobe fitouts complete
18/09/2013 - mirrors installed to bathrooms, WIR and furniture recess
19/09/2013 - water tank installed, flyscreens installed
19/09/2013 - yard cleanup
20/09/2013 - glass splashback installed in kitchen
24/09/2013 - painters return and paint feature wall in main bedroom
27/09/2013 - cook top & range hood installed in kitchen
27/09/2013 - carpenters fit door handles to internal doors, install towel rails to bathrooms
30/09/2013 - practical completion inspection with our sire supervisor, minor issues to be addressed
Friday, 16 August 2013
August 2013
2/8/2013 - gyprock and cornice delivered
14/8/2013 - gyprock is complete, ceiling to alfresco complete
16/8/2013 - front door & laundry door installed, garage door installed, house is locked-up!
16/8/2013 - internal doors and skirting boards delivered
19/8/2013 - kitchen arrives & installed
20/08/2013 - kitchen rangehood installed
20/08/2013 - internal doors, skirting boards & timber reveals installed
21/08/2013 - cornices and gyprock is complete
22/08/2013 - shelving units installed to dining, home theatre and hallway
22/08/2013 - waterproofing to wet areas is complete
23/08/2013 - vanity units installed to bathroom & ensuite
23/08/2013 - laundry cupboards installed
27/08/2013 - tiling to wet areas commenced
28/08/2013 - tiling complete
30/08/2013 - final measure and quote for floor & window coverings
30/08/2013 - painters arrive and commence undercoating