6/6/2013 - kordon termite barrier installed
11/6/2013 - house frame arrives, framing commences
14/6/2013 - windows arrive
17/6/2013 - house frame & roof trusses completed
18/6/2013 - bricks arrive
21/6/2013 - bricklayers arrive
22/6/2013 - bad weather sets in, rains for 8 days
late June - blocked drain on the laneway