Saturday, 22 June 2013

June 2013

5/6/2013 - concrete slab is complete
6/6/2013 - kordon termite barrier installed
11/6/2013 - house frame arrives, framing commences
14/6/2013 - windows arrive
17/6/2013 - house frame & roof trusses completed
18/6/2013 - bricks arrive
21/6/2013 - bricklayers arrive
22/6/2013 - bad weather sets in, rains for 8 days
late June - blocked drain on the laneway








May 2013

7/5/2013 - the block is pegged out for excavation
11/5/2013 - excavation begins, the block is levelled
20/5/2013- plumbing commences
31/5/2013 - construction of the concrete slab commences




Friday, 21 June 2013

Formalities


21 Oct 2012 - tender signed
12 Dec 2012 - land is settled
7 Feb 2013 - contract signed
26 Apr 2013 - plans approved