1/7/2013 - after 8 days of rain the fine weather returns
2/7/2013 - bricklayers return and complete the back of the house
4/7/2013 - bricklayers complete the southern wall of the house
8/7/2013 - bricklayers complete the front of the house
10/7/2013 - bricklaying is complete
10/7/2013 - electricity pillar box is installed and power is connected to the house
12/7/2013 - guttering & fascia is delivered
13/7/2013 - site cleaned, spare bricks moved to rear of the property
16/7/2013 - guttering, fascia & roof battens complete, roof scaffold in place, bricks cleaned
18/7/2013 - colorbond roof is complete
24/7/2013 - internal sliding door cavities installed
25/7/2013 - plumbing rough-in complete
26/7/2013 - electrical rough-in complete, eaves complete
29/7/2013 - merbau timber installed to house facade
30/7/2013 - walk thru with site supervisor