1/8/2013 - wall and ceiling insulation complete
2/8/2013 - gyprock and cornice delivered
14/8/2013 - gyprock is complete, ceiling to alfresco complete
16/8/2013 - front door & laundry door installed, garage door installed, house is locked-up!
16/8/2013 - internal doors and skirting boards delivered
19/8/2013 - kitchen arrives & installed
20/08/2013 - kitchen rangehood installed
20/08/2013 - internal doors, skirting boards & timber reveals installed
21/08/2013 - cornices and gyprock is complete
22/08/2013 - shelving units installed to dining, home theatre and hallway
22/08/2013 - waterproofing to wet areas is complete
23/08/2013 - vanity units installed to bathroom & ensuite
23/08/2013 - laundry cupboards installed
27/08/2013 - tiling to wet areas commenced
28/08/2013 - tiling complete
30/08/2013 - final measure and quote for floor & window coverings
30/08/2013 - painters arrive and commence undercoating