04/09/2013 - caesar stone benchtops installed
05/09/2013 - vanity basins installed
05/09/2013 - gas connected to house
06/09/2013 - painters complete external painting
11/09/2013 - painting complete
12/09/2013 - tiling to ensuite bathroom complete
13/09/2013 - lights installed, electrical fitout is complete
13/09/2013 - internal plumbing complete
17/09/2013 - internal cleaners arrive
18/09/2013 - security fence removed
18/09/2013 - wardrobe fitouts complete
18/09/2013 - mirrors installed to bathrooms, WIR and furniture recess
19/09/2013 - water tank installed, flyscreens installed
19/09/2013 - yard cleanup
20/09/2013 - glass splashback installed in kitchen
24/09/2013 - painters return and paint feature wall in main bedroom
27/09/2013 - cook top & range hood installed in kitchen
27/09/2013 - carpenters fit door handles to internal doors, install towel rails to bathrooms
30/09/2013 - practical completion inspection with our sire supervisor, minor issues to be addressed