2/10/2013 - painters return and address some touch-up issues
3/10/2013 - cleaners arrive and address cleaning issues
4/10/2013 - handover with our site supervisor, the house is now ours
4/10/2013 - security system installed
8/10/2013 - stormwater drainage complete, our WCC bins are delivered
9/10/2013 - timber floor installation commences
9/10/2013 - concreting team commence formwork to paths and driveway
11/10/2013 - timber floor to living rooms is complete, carpet installed to bedrooms
11/10/2013 - landscaper arrives and commences work on retaining wall in back yard
11/10/2013 - contracts exchanged on the old family home, the house is sold
14/10/2013 - concreting to paths and driveway is complete
15/10/2013 - blinds and security doors installed
22/10/2013 - landscapers turf the back yard
23/10/2013 - landscapers install deck to front verandah and complete garden feature
24/10/2013 - landscapers turf the front yard and form front garden
25/10/2013 - carpenters return to install skirting boards
25/10/2013 - boundary fencing is complete
26/10/2013 - harvey norman arrives with our new fridge, dishwasher and smart tv