Friday, 6 September 2013

September 2013

04/09/2013 - caesar stone benchtops installed
05/09/2013 - vanity basins installed
05/09/2013 - gas connected to house
06/09/2013 - painters complete external painting
11/09/2013 - painting complete
12/09/2013 - tiling to ensuite bathroom complete
13/09/2013 - lights installed, electrical fitout is complete
13/09/2013 - internal plumbing complete
17/09/2013 - internal cleaners arrive
18/09/2013 - security fence removed
18/09/2013 - wardrobe fitouts complete
18/09/2013 - mirrors installed to bathrooms, WIR and furniture recess
19/09/2013 - water tank installed, flyscreens installed
19/09/2013 - yard cleanup
20/09/2013 - glass splashback installed in kitchen
24/09/2013 - painters return and paint feature wall in main bedroom
27/09/2013 - cook top & range hood installed in kitchen
27/09/2013 - carpenters fit door handles to internal doors, install towel rails to bathrooms
30/09/2013 - practical completion inspection with our sire supervisor, minor issues to be addressed






 































Friday, 16 August 2013

August 2013

1/8/2013 - wall and ceiling insulation complete
2/8/2013 - gyprock and cornice delivered
14/8/2013 - gyprock is complete, ceiling to alfresco complete
16/8/2013 - front door & laundry door installed, garage door installed, house is locked-up!
16/8/2013 - internal doors and skirting boards delivered
19/8/2013 - kitchen arrives & installed
20/08/2013 - kitchen rangehood installed
20/08/2013 - internal doors, skirting boards & timber reveals installed
21/08/2013 - cornices and gyprock is complete
22/08/2013 - shelving units installed to dining, home theatre and hallway
22/08/2013 - waterproofing to wet areas is complete
23/08/2013 - vanity units installed to bathroom & ensuite
23/08/2013 - laundry cupboards installed
27/08/2013 - tiling to wet areas commenced
28/08/2013 - tiling complete
30/08/2013 - final measure and quote for floor & window coverings
30/08/2013 - painters arrive and commence undercoating

















Sunday, 14 July 2013

July 2013

1/7/2013 - after 8 days of rain the fine weather returns
2/7/2013 - bricklayers return and complete the back of the house
4/7/2013 - bricklayers complete the southern wall of the house
8/7/2013 - bricklayers complete the front of the house
10/7/2013 - bricklaying is complete
10/7/2013 - electricity pillar box is installed and power is connected to the house
12/7/2013 - guttering & fascia is delivered
13/7/2013 - site cleaned, spare bricks moved to rear of the property
16/7/2013 - guttering, fascia & roof battens complete, roof scaffold in place, bricks cleaned
18/7/2013 - colorbond roof is complete
24/7/2013 - internal sliding door cavities installed
25/7/2013 - plumbing rough-in complete
26/7/2013 - electrical rough-in complete, eaves complete
29/7/2013 - merbau timber installed to house facade
30/7/2013 - walk thru with site supervisor






























Saturday, 22 June 2013

June 2013

5/6/2013 - concrete slab is complete
6/6/2013 - kordon termite barrier installed
11/6/2013 - house frame arrives, framing commences
14/6/2013 - windows arrive
17/6/2013 - house frame & roof trusses completed
18/6/2013 - bricks arrive
21/6/2013 - bricklayers arrive
22/6/2013 - bad weather sets in, rains for 8 days
late June - blocked drain on the laneway








May 2013

7/5/2013 - the block is pegged out for excavation
11/5/2013 - excavation begins, the block is levelled
20/5/2013- plumbing commences
31/5/2013 - construction of the concrete slab commences




Friday, 21 June 2013

Formalities


21 Oct 2012 - tender signed
12 Dec 2012 - land is settled
7 Feb 2013 - contract signed
26 Apr 2013 - plans approved